The build graph is the plan; tasks are the units of work Terrabuild schedules to carry it out.

What is a Task?

A task is one target applied to one project—for example, “run the build target for project X.” When you run terrabuild run build, Terrabuild selects the relevant project targets and represents each one as a task in the graph.

The target supplies the commands and behavior; the project supplies the files, dependencies, and variables. Together they give Terrabuild everything it needs to schedule the task correctly.

From Selection to Completion

Every run follows the same broad sequence:

  1. Select — Terrabuild starts from the requested target and discovers the tasks required by its dependencies and phases.
  2. Plan — It validates the graph, orders dependent work, and identifies tasks that may run concurrently.
  3. Resolve — When a task becomes ready, Terrabuild determines whether it must execute or whether an earlier result can be reused.
  4. Complete — The task produces a result that unlocks its dependents; independent tasks continue in parallel.

Dependencies are readiness constraints, not a serial execution list. A task waits only for the work it depends on, so unrelated branches of the graph can progress at the same time.

Task Outcomes

Scheduling tells Terrabuild when a task may proceed. Once ready, the task resolves to one of three outcomes:

ActionDescription
BuildExecute the target commands
RestoreRestore a successful cache hit
SummaryReport a previous failed cached run without executing commands or restoring outputs

The task graph treats each outcome as completion, but only a successful build or restore can satisfy work that requires successful outputs. If a task fails, its dependents do not run.

The next page, Caching, explains how Terrabuild computes reusable identities and chooses between these outcomes.

Propagating Work

If a task builds instead of restoring, dependent tasks are also marked for build unless that dependency uses build = ~lazy. This keeps downstream outputs consistent after real work occurs while allowing lazy setup targets to avoid unnecessary rebuild propagation.

Task scheduling also respects workspace-wide phases and may combine compatible tasks into batch builds. Those features change how work is grouped or ordered; they do not change what a task represents.